E10 is the fast track process in dealing with construction permits. The spirit behind this initiative is close interaction between investor and Kulim Municipal Council to facilitate constructions works and ultimately products exportable within 10 months.
Appoint PSP/Local Consultant (Associate Town Planner/ Architect/Engineer)
PREPARE PROJECT BRIEF 1. Introduction (Company Background, Total Of Project Investment & Product) 2. List Of Principle Submitting Person (PSP) 3. Planning Permission 4. Earth Work Plan 5. Building Plan 6. Road & Drainage Plan 7. Workers Residential Complex Plan 8. Provisional Approval Application Letter 9. Process Plan Fees 10. Timeline Project 11. Site Monitoring System (CCTV) 12. Slide Presentation (Project Brief)
PROJECT BRIEF ENDORSEMENT Submission For Planning Permission Provisional Approval (PA) Granted for TLQ and preliminary works to be completed within 14 Days